The loop is designed for material and radioactivity transport investigation under PWR/VVER conditions. The RVS-3 loop facility enables the performance of irradiation experiments in a wide range of operational parameters limited by maximum parameters as listed below.
Maximum Parameters
The loop is a closed stainless steel system with typical technological auxiliary systems. The experimental equipment of the loop consists of:Description
Pressure | 16.5 MPa |
Temperature | 345 °C |
Cooling water flow rate | 10 000 kg/h |
Neutron flux (E > 1 MeV) | ~ × 1018 |
Neutron flux (E thermal) | ~ × 1018 |
Power demand | 120 kW |
Active (in-pile) channel situated in the reactor core for irradiation of materials samples
- Out-of-pile test section providing the same thermal-hydraulic parameters as in-pile channel
- Electrically heated rods for corrosion tests of materials
- Possible loading facility for investigation of corrosion fatigue at low-cycle load and SSRT test
- Filtration system equipped with mechanical and ion exchange filters
- Make-up water system for water environment preparation and dosing into the loop system
- Sampling system for water sampling from different points of the loop
- High-temperature sensors for water chemistry monitoring
Experimental possibilities
- Investigation of degradation and corrosion behaviour of structural materials’ mechanical properties under irradiation and PWR/VVER water chemistry and thermal-hydraulic conditions
- Investigation of behaviour (corrosion, hydriding) of fuel cladding materials under influence of irradiation, thermal flux and water chemistry conditions
- Investigation of radioactivity transport and behaviour under PWR/VVER conditions
- Testing of high-temperature, high-pressure sensors for water chemistry monitoring
- Research of corrosion products transport, influence of water environment
- High-temperature monitoring of water regimes testing
RVS-3 Loop Chart
1 main circulation pump;
2 electrical heater;
3 out-of-pile test section;
4 active channel;
5 cooler;
6 pressurizer;
7 filtration circuit
2 electrical heater;
3 out-of-pile test section;
4 active channel;
5 cooler;
6 pressurizer;
7 filtration circuit